Heritage Final Assembly Pits & Floor

The Heritage Final Assembly Plant embraces sustainable design. DSP literally laid the ground floor from which the modern plant could be launched. In early 2003, utilizing our skilled trade labor, we completed a concrete slab-on-grade and concrete process pits project for the Heritage Plant at the Rouge Complex in Dearborn, Michigan.

Highlights include:

  • Fiber reinforced concrete floor
  • 1,000,000 sf of floor created
  • 24 process pits created
  • Some pits were 300 ft. long & 18 ft. deep
  • Over 25,000 cy of concrete
  • 14,000 yds. poured in 12 weeks
  • Largest pour in one week: 1,557 yds.
  • Flat floor with a tolerance of FF35/FL25
  • Heritage Plant is Gold LEED Certified by the U.S Green Building Council